kThe Ledger.nuclear.events
As of Oct 26, 2026Seed data · Deal Tracker Oct 23, 2026Evidence graded A–E

The 30-second answer

How much nuclear power is actually under binding contract in the data-center and public-power deal book?

14.2 GW is binding (deal tiers 1–3). 95% of it comes from reactors that already exist.

a Binding · existing, restarted or uprated

13.5 GW

9,617 MW from operating plants (Tier 1) + 3,864 MW from restarts and uprates (Tier 2).

b Binding · new reactors

0.67 GW

3 units of new build with a binding buyer: 670 MW.

c Non-binding pipeline · tiers 5–8

43.8 GW

3.1× the binding total. Largest single line: Oklo–Switch, 12 GW, non-binding by its own terms.

a · existing/restart/uprateb · new reactorsTier 4 equity (320 MW, Cascade Phase 1)c · non-binding, tiers 5–8

What the number does and doesn’t say
  • The three binding new reactors:
    • Hermes 2 — 50 MWe; PPA Aug 2025; groundbreaking Apr 2026; target 2030. A
    • Long Mott Generating Station — 4 × Xe-100 ≈ 320 MWe (+ process heat); NRC final SE targeted Nov 2026. A
    • Darlington BWRX-300 Unit 1 — ~300 MWe (Unit 1 of 4); Approved May 8, 2025; complete end-2029; grid 2030. B
  • Not yet cut by delivery date. Several binding rows land in 2030 or later (the Meta and Amazon uprate shares, part of Google’s PJM uprates, Hermes 2, Darlington Unit 1). A strict before-2030 cut comes with the Control Room.
  • MWe as claimed by the parties, not metered delivery. Fusion comparators and rows with no stated MW are left out of the totals; nested sub-deals are counted once.
  • Seed figures from the Deal Tracker as of Oct 23, 2026, checked Oct 26, 2026. Full rules on the Method page; the underlying data are in meta.json and deals.json.

Multiplication factor bands

k < 1

Subcritical

Announced, MOU’d, pre-application or unfunded. Needs outside neutrons to keep going.

44.1 GW · 23 deals

k = 1

Critical

Self-sustaining evidence: binding offtake, docketed review or permit, financing closed, not yet producing.

3.7 GW · 9 deals

k > 1

Supercritical

Adding energy: operating plants under contract, or fuel in the core.

10.4 GW · 8 deals

The limiting factor sets the band. A deal view reads the offtake, so Kemmerer, under construction with no verified buyer, sits at k < 1. How bands are assigned.

Pipeline by deal tier

Claimed MWe, fission only · 42 deals · as of Oct 23, 2026

TierWhat binds the buyerDealsMW countedScale
1Binding PPA, operating plant79,617 MW
2Restart/uprate with offtaker73,864 MW
3Binding offtake, new reactor5670 MW
4Offtaker equity1320 MW
5Development/site with milestones77,445 MW
6Framework / MOU / GW target927,840 MW
7RFP / LOI / exploring68,498 MW
8'Nuclear-powered' campus, no vendor/license/fuel None classed yet; Fermi America (Tier 7) is closest.0—

Tier is set by the strongest evidence that binds the buyer, not by the headline. A grade-A docket can sit on a Tier 7 deal (Fermi America), and a grade-C press release can describe a Tier 1 PPA.

From the Promise Ledger

Log excerpt · 45 promises tracked: 2 delivered, 13 slipped, 1 dropped, 1 cancelled, 28 pending

PromisorPromiseTargetStatusSlippage / outcomeGradeSource
TerraPowerNatrium Kemmerer Unit 1 operating (345 MWe)2028 → 2031 (grid)slipped~36 months; HALEU delay disclosed Dec 2022AFR 2026-05067
HoltecReturn Palisades (805 MW) to serviceQ4 2025 → no new grid dateslipped≥10 months; fuel load began Aug 30, 2026AFR 2026-21594
UAMPS / NuScaleCarbon Free Power Project, 462 MWeTerminated Nov 8, 2023cancelledTarget price 1.53× ($58 → $89/MWh)ANuScale 8-K
DOE Reactor Pilot ProgramAt least 3 test reactors critical by Jul 4, 2026Jul 4, 2026deliveredMet: 4 criticalities, all zero-power; 7 other selectees missed the dateBDOE, 4th criticality
Constellation / MicrosoftRestart Crane (TMI-1), 835 MW2028 → 2027pending−12 months (ahead of plan)AFR 2026-19603

Rows are never deleted. When a date moves, the new outcome is appended and the original stays. Credit where due: the DOE pilot goal was met, and Crane is running ahead of plan. More rows from the ledger.

Go further

Load listDealsAll 42 tracked deals by tier, with MW counted, k-band, grade and as-of date. Equipment listEntities18 vendors, utilities, buyers and fuel suppliers: design, ticker, licensing rung and a one-line status. Outage logPromisesDated promises that slipped, were dropped or cancelled, and the ones that were kept. Shift BriefThis weekWhat changed on the docket and in the deal book, logged plant-style, with grades and sources. Tech SpecMethodEvidence grades, deal tiers, licensing ladder, k-bands, as-of rules and the correction policy. ReferenceGlossaryThe acronyms and terms of art, with a “watch for” note where marketing bends them.
Coming soonControl RoomPlanned paid layer: the full deal table with contract terms and source packs, the complete promise history, entity dossiers, a 90-day regulatory calendar, the Shift Brief archive and exportable exhibit packs.