As of Oct 26, 2026Seed data · Deal Tracker Oct 23, 2026Evidence graded A–E

Load list · every tracked deal, by the strength of what binds the buyer

Deals

42 deals. 14,151 MW are binding (tiers 1–3), and 95% of that comes from reactors that already exist. Tiers 5–8 add 43,783 MW of options, frameworks and letters, 3.09× the binding total. Tier rules are in the Method.

MW counted, by tier

Each block is one deal · fission only · as of Oct 23, 2026

1 Binding PPA, operating plant9,617 MW7 deals
2 Restart/uprate with offtaker3,864 MW7 deals
3 Binding offtake, new reactor670 MW5 deals
4 Offtaker equity320 MW1 deal
5 Development/site with milestones7,445 MW7 deals
6 Framework / MOU / GW target27,840 MW9 deals
7 RFP / LOI / exploring8,498 MW6 deals
8 'Nuclear-powered' campus, no vendor/license/fuelno deals0 deals

Rows with no stated MW, and the two fusion comparators, are listed below but not counted. Totals are not yet cut by delivery date; see the Method.

The deal list

Open a deal name for a short detail view · contract terms are not shown

All 42 tracked deals with tier, MW counted, k-band, evidence grade and as-of date
DealPartiesTierMW countedk-bandGradeAs of
Tier 1 · Binding PPA, operating plant (binding)
Constellation existing-fleet supply
Category
Large LWR
Deployment
Utility grid unit (PJM)
Licensing rung
5 (operating)
Lead source
Constellation (full source pack in the Control Room)
Constellation ↔ Google12,700k>1COct 23, 2026
Perry + Davis-Besse PPAs
Category
Large LWR
Deployment
Utility grid unit (PJM)
Licensing rung
5 (operating)
Lead source
Meta (full source pack in the Control Room)
Vistra ↔ Meta12,176k>1COct 23, 2026
Susquehanna PPA (amended)
Category
Large LWR
Deployment
Utility grid unit (front-of-meter since Apr 2026; was co-located)
Licensing rung
5 (operating)
Lead source
Talen PR (full source pack in the Control Room)
Talen Energy ↔ Amazon (AWS)11,920k>1AOct 23, 2026
Comanche Peak PPA
Category
Large LWR
Deployment
Co-located data center (1,200 MW load directly connected, per PUCT filing)
Licensing rung
5 (operating)
Lead source
Vistra Q4-25 (full source pack in the Control Room)
Vistra ↔ Amazon Data Services (AWS named Feb 2026)11,200k>1AOct 23, 2026
Clinton PPA + relicense
Category
Large LWR
Deployment
Utility grid unit (MISO)
Licensing rung
5 (operating; renewed to Apr 2047, Dec 2025)
Lead source
DCF (full source pack in the Control Room)
Constellation ↔ Meta11,121k>1COct 23, 2026
Calvert Cliffs PPA (existing share)
Category
Large LWR
Deployment
Utility grid unit (PJM; on-site campus withdrawn)
Licensing rung
5 (operating)
Lead source
DCF (full source pack in the Control Room)
Constellation ↔ Amazon1500k>1COct 23, 2026
Loviisa PPA (Finland)
Category
Large LWR
Deployment
Utility grid unit (non-US)
Licensing rung
5 (operating)
Lead source
NNN (full source pack in the Control Room)
Fortum ↔ Google1not countedMW not statedk>1DOct 23, 2026
Tier 2 · Restart/uprate with offtaker (binding)
PJM fleet uprates (11 units)
Category
Restart/uprate
Deployment
Utility grid unit (PJM)
Licensing rung
4 (uprate LAR filings not checked)
Lead source
Constellation (full source pack in the Control Room)
Constellation ↔ Google2890k=1COct 23, 2026
Crane (TMI-1) restart
Category
Restart/uprate
Deployment
Utility grid unit (PJM)
Licensing rung
4 (OL to Apr 19, 2034; restart exemption + 3 LARs pending)
Lead source
DOE EDF (full source pack in the Control Room)
Constellation ↔ Microsoft2835k=1AOct 23, 2026
Palisades restart
Category
Restart/uprate
Deployment
Utility grid unit (MISO)
Licensing rung
5 (fuel load in progress)
Lead source
FR 2026-21594 (full source pack in the Control Room)
Holtec ↔ Wolverine + Hoosier co-ops2805k>1AOct 23, 2026
Duane Arnold restart
Category
Restart/uprate
Deployment
Utility grid unit (MISO)
Licensing rung
4 (restart approvals pending; NRC decision target Jan 29, 2028)
Lead source
NextEra (full source pack in the Control Room)
NextEra ↔ Google (CIPCO takes remainder)2615k=1AOct 23, 2026
Perry / Davis-Besse / Beaver Valley uprates
Category
Restart/uprate
Deployment
Utility grid unit (PJM)
Licensing rung
4 (uprate LAR filings not checked)
Lead source
DCF (full source pack in the Control Room)
Vistra ↔ Meta2433k=1COct 23, 2026
Calvert Cliffs uprate share
Category
Restart/uprate
Deployment
Utility grid unit (PJM)
Licensing rung
4
Lead source
DCF (full source pack in the Control Room)
Constellation ↔ Amazon2190k=1COct 23, 2026
Vogtle 1–2 / Hatch NU-1 uprates
Category
Restart/uprate
Deployment
Utility grid unit
Licensing rung
4 (NRC uprate approvals pending)
Lead source
DCF (full source pack in the Control Room)
Georgia Power ↔ Google (tariff, not PPA)296k=1DOct 23, 2026
Tier 3 · Binding offtake, new reactor (binding)
Long Mott Generating Station
Category
Advanced/Gen IV
Deployment
Behind-the-meter industrial
Licensing rung
2 (docketed; ACRS supported issuance Oct 16, 2026)
Lead source
NRC Long Mott (full source pack in the Control Room)
Dow ↔ X-energy (DOE ARDP)3320k=1AOct 23, 2026
Darlington BWRX-300 Unit 1
Category
SMR (LWR)
Deployment
Utility grid unit
Licensing rung
3 (licence to construct)
Lead source
Ontario (full source pack in the Control Room)
OPG (Ontario crown utility) / GE Vernova Hitachi3300k=1BOct 23, 2026
Hermes 2
Category
Advanced/Gen IV
Deployment
Utility grid unit (TVA, serves Google DCs)
Licensing rung
3 (CP 2024)
Lead source
Neutron Bytes (full source pack in the Control Room)
Kairos ↔ TVA PPA ↔ Google350k=1AOct 23, 2026
Orion fusion PPA (comparator)
Category
Fusion (comparator)
Deployment
Utility grid unit
Licensing rung
n/a
Lead source
Axios (full source pack in the Control Room)
Helion ↔ Microsoft3not countedcomparatornoneDOct 23, 2026
ARC offtake (comparator)
Category
Fusion (comparator)
Deployment
Utility grid unit
Licensing rung
n/a
Lead source
NNN (full source pack in the Control Room)
Commonwealth Fusion Systems ↔ Google3not countedcomparatornoneCOct 23, 2026
Tier 4 · Offtaker equity (equity)
Cascade Advanced Energy Facility
Category
Advanced/Gen IV
Deployment
Utility grid unit (public power owner)
Licensing rung
1 (pre-application)
Lead source
NRC pre-app (full source pack in the Control Room)
Energy Northwest ↔ X-energy ↔ Amazon (led $700M Series C-1)4320k<1AOct 23, 2026
Tier 5 · Development/site with milestones (non-binding)
Natrium fleet (2 funded + 6 rights)
Category
Advanced/Gen IV
Deployment
Utility grid unit (sites TBD)
Licensing rung
1 (no site docketed)
Lead source
TerraPower (full source pack in the Control Room)
TerraPower ↔ Meta52,800k<1COct 23, 2026
V.C. Summer 2–3 completion
Category
Large LWR
Deployment
Utility grid unit
Licensing rung
1 (COLs terminated 2019)
Lead source
Reuters (full source pack in the Control Room)
Santee Cooper ↔ Brookfield52,200k<1COct 23, 2026
Pike County OH Aurora campus
Category
Advanced/Gen IV
Deployment
Utility grid unit (former Portsmouth GDP site)
Licensing rung
1 (Aurora COLA denied Jan 2022; pre-app)
Lead source
Oklo 10-K (full source pack in the Control Room)
Oklo ↔ Meta (prepayment)51,200k<1AOct 23, 2026
Palisades Pioneer 1–2 (SMR-300)
Category
SMR (LWR)
Deployment
Utility grid unit
Licensing rung
2 (dockets 50-616/617)
Lead source
FR 2026-03943 (full source pack in the Control Room)
Holtec + Hyundai E&C5600k<1AOct 23, 2026
Kemmerer Unit 1 (Natrium)
Category
Advanced/Gen IV
Deployment
Utility grid unit
Licensing rung
3 (CPAR-1)
Lead source
FR 2026-05067 (full source pack in the Control Room)
TerraPower (DOE ARDP); offtaker not verified5345k<1AOct 23, 2026
Clinch River BWRX-300
Category
SMR (LWR)
Deployment
Utility grid unit
Licensing rung
3 (CPAR-2)
Lead source
FR 2026-20345 (full source pack in the Control Room)
TVA (self-build)5300k<1AOct 23, 2026
Army Janus (5 bases)
Category
Microreactor
Deployment
Federal/military
Licensing rung
Army authorization (tracked separately)
Lead source
army.mil (full source pack in the Control Room)
Army ↔ Antares, BWXT, General Atomics, Radiant, Westinghouse5not countedMW not statedk<1AOct 23, 2026
Tier 6 · Framework / MOU / GW target (non-binding)
Switch master power agreement
Category
Advanced/Gen IV
Deployment
Co-located data center (sites TBD)
Licensing rung
1
Lead source
Reuters (full source pack in the Control Room)
Oklo ↔ Switch612,000k<1COct 23, 2026
TVA–ENTRA1 NuScale program
Category
SMR (LWR)
Deployment
Utility grid unit
Licensing rung
1 (no site)
Lead source
Motley Fool (full source pack in the Control Room)
ENTRA1 ↔ TVA (NuScale technology)66,000k<1DOct 23, 2026
X-energy 5 GW partnership (remainder)
Category
Advanced/Gen IV
Deployment
Utility grid unit
Licensing rung
—
Lead source
Amazon (full source pack in the Control Room)
Amazon ↔ X-energy ↔ KHNP ↔ Doosan63,080k<1COct 23, 2026
Endeavour / Edged co-development
Category
SMR (LWR)
Deployment
Co-located data center
Licensing rung
—
Lead source
NNN (full source pack in the Control Room)
Deep Fission ↔ Endeavour62,000k<1COct 23, 2026
Elementl three-site program
Category
Advanced/Gen IV
Deployment
Utility grid unit (tech TBD)
Licensing rung
—
Lead source
Elementl (full source pack in the Control Room)
Elementl Power ↔ Google61,800k<1COct 23, 2026
Port of Victoria (Blue Energy)
Category
SMR (LWR)
Deployment
Co-located data center
Licensing rung
2 (docket 99902137; ML26265A371)
Lead source
FR 2026-20678 (full source pack in the Control Room)
Blue Energy ↔ Crusoe61,500k<1AOct 23, 2026
Indiana Xe-100 plant (Breed site)
Category
Advanced/Gen IV
Deployment
Utility grid unit
Licensing rung
—
Lead source
Amazon (full source pack in the Control Room)
Amazon ↔ X-energy ↔ AEP / I&M6960k<1COct 23, 2026
Kairos master agreement (remainder)
Category
Advanced/Gen IV
Deployment
Utility grid unit
Licensing rung
—
Lead source
Kairos (full source pack in the Control Room)
Kairos ↔ Google6450k<1COct 23, 2026
Crusoe–Aalo partnership
Category
Microreactor
Deployment
Co-located data center
Licensing rung
DOE (Aalo-X critical Jul 4, 2026)
Lead source
NNN (full source pack in the Control Room)
Aalo Atomics ↔ Crusoe650k<1COct 23, 2026
Tier 7 · RFP / LOI / exploring (non-binding)
Project Matador AP1000 ×4
Category
Large LWR
Deployment
Co-located data center
Licensing rung
2 (docketed; NRC-2026-0100; ML26261A417)
Lead source
FR 2026-20742 (full source pack in the Control Room)
Fermi America (Westinghouse tech; no nuclear offtaker)74,400k<1AOct 23, 2026
Standard Power SMR plan
Category
SMR (LWR)
Deployment
Co-located data center
Licensing rung
—
Lead source
NNN (full source pack in the Control Room)
Standard Power ↔ NuScale / ENTRA171,848k<1COct 23, 2026
Equinix pre-agreements
Category
Advanced/Gen IV
Deployment
Co-located data center
Licensing rung
—
Lead source
Equinix (full source pack in the Control Room)
Equinix ↔ Oklo, ULC-Energy/Rolls-Royce, Stellaria, Radiant71,250k<1COct 23, 2026
NYPA upstate advanced nuclear
Category
Large LWR
Deployment
Utility grid unit (tech TBD)
Licensing rung
—
Lead source
NYPA (full source pack in the Control Room)
NYPA (RFQ; 8 communities, 23 developers responded)71,000k<1COct 23, 2026
North Anna SMR study
Category
SMR (LWR)
Deployment
Utility grid unit
Licensing rung
—
Lead source
NNN (full source pack in the Control Room)
Dominion ↔ Amazon7not countedMW not statedk<1COct 23, 2026
Sabey–TerraPower MOU
Category
Advanced/Gen IV
Deployment
Co-located data center
Licensing rung
—
Lead source
NNN (full source pack in the Control Room)
TerraPower ↔ Sabey Data Centers7not countedMW not statedk<1COct 23, 2026

Full deal table and source packs in the Control Room Control Room · coming soon: status, bridging power, delivery dates, contract terms and every source behind each row.

Download the public fields: data/deals.json · data/meta.json.